S/N |
Project Title |
Sector of Intervention |
Remarks |
|
Level of Physical Implementation |
% of Work done & CERTIFIED |
|||
1 |
Construction of Clinic | Works | All defects have been rectified. | 100% completed and handed over |
2 |
Construction of 2-storey office block for GCMA | Works | In use | Main Building completed and in use. |
3 |
2-storey 6-Unit classroom block with library, computer laboratory and head Teachers office | Works | Awaiting handing over | 100% Completed |
4 |
Const. of Generator Platform, 40 footer container stand & Polytank double platform | Works | Awaiting handing over | 100% Completed |
5 |
Drainage works at Kwashieman Church road- Kwashiebu | Urban Roads | Completed | 100% |
6 |
Construction of 0.6m U drain around Research road -Sowutuom | Urban Roads | Completed | 100% |
7 |
Construction of Speed Humps on selected roads within Ga Central | Urban Roads | Completed | 100% |