S/N |
Project Title |
Sector of Intervention |
Remarks |
|
Level of Physical Implementation |
% of Work done & CERTIFIED |
|||
1 |
Construction of 2-storey Fire Service Building at Anyaa. | Works | Work is ongoing | 82% complete |
2 |
Construction of 3-Storey Health Centre |
Works | Work is ongoing | 82% complete |
3 |
Drainage works at block factory road Race Course | Urban Roads | Ongoing | 40% Completed |